Northern Division Overtaking Opportunities - Nutts Corner Roundabout DALs

Scheme signboard

Tully Road exit (towards Antrim)

Overall length:0.65 kilometres
Overtaking Length:                                0.31 kilometres
Cost:£0.35 million
Type:Differential Acceleration Lane
Contract:Traditional Consultant Design Contractor Build
Contractor:John McQuillan Contracts
Status:Open to traffic April 2006

The differential acceleration lane widened the A26 Tully Road to create an overtaking opportunity for northwest bound traffic departing the Nutts Corner Roundabout. The online improvement symmetrically widened the existing road to 12 metres and is marked as two lanes (3.2 metre wide nearside lane and 3.4 metre wide overtaking lane)  towards Antrim and one lane (3.4 metres wide) towards the roundabout, with opposing traffic streams separated by a double white line system. The running carriageway is flanked either side by 1 metre wide edge strips. A ghost island was included to promote safe right turns into a goods distribution depot. Two new 60 metre long by 3.5 metre wide lanes increased the capacity of the approach to the Nutts Corner Roundabout.

Moira Road exit (towards Moira)

Overall length:1.0 kilometres
Overtaking Length:                                0.8 kilometres
Cost:£0.52 million
Type:Differential Acceleration Lane
Contract:Traditional Consultant Design Contractor Build
Contractor:John McQuillan Contracts
Status:Open to traffic April 2006

The differential acceleration lane widened the A26 Moira Road to create an overtaking opportunity for southwest bound traffic departing the Nutts Corner Roundabout. The online improvement symmetrically widened the existing road to 12 metres and is marked as two lanes (3.2 metre wide nearside lane and 3.4 metre wide overtaking lane) towards Moira and one lane (3.4 metres wide) towards the roundabout, with opposing traffic streams separated by a double white line system. The running carriageway is flanked either side by 1 metre wide edge strips. Two new 60 metre long by 3.5 metre wide lanes increased the capacity of the approach to the Nutts Corner Roundabout.

Photo gallery

(click on thumbnail to enlarge)

Before construction

Location on Northern Key Transport Corridor    Tully Road exit before construction of DAL    Moira Road exit before construction of DAL

Completed scheme

Tully Road Exit after construction of DAL    TullyToad exit after construction of DAL    Moira Road exit after construction of DAL    Moira Road exit after construction of DAL