Northern Division Overtaking Opportunities - Greenmount Roundabout DAL

Scheme signboard

Overall Length:0.82 kilometres
Overtaking Lenght:                   0.64 kilometres
Cost:£0.3 million
Type:Differential Acceleration Lane
Contract:Traditional Consultant Design Contractor Build
Contractor:Maxwell
Status:Open to traffic April 2001

The differential acceleration lane widened the A29 Dunhill Road to create an overtaking opportunity for west bound traffic departing the Greenmount Roundabout. The online improvement symmetrically widened the existing road to 12 metres and is marked as two lanes (3.2 metre wide nearside lane and 3.4 metre wide overtaking lane) uphill towards Limavady and one lane (3.4 metres wide) downhill towards Coleraine, with opposing traffic lanes separated by a double white line system. The running carriageway is flanked either side by 1 metre wide edge strips. A ghost island was included to promote safe right turns into Greenmount Road close to the Greenmount Roundabout.

Photo gallery

(click on thumbnail to enlarge)

Before construction

Location on Northern Key Transport Corridor

During Construction

Greenmount DAL - under construction

Completed scheme

Greenmount DAL - roundabout exit towards Limavady